Downtown Lebanon Tunnel Rehabilitation

General Information

Welcome to the Downtown Lebanon Tunnel Rehabilitation project page. This page contains updates, contact information, documents, and answers to frequently asked questions pertaining to this project. New information is added as it is received. You can subscribe to receive alerts by subscribing to our LebAlert Service

Background information about this project can be found on our Downtown Visioning Study & Tunnel Project page. You can easily find this page again by going to LebanonNH.gov/Tunnel. 

  1. Project Information
  2. Project Alerts

This project is complete with the exception of minor construction follow-up. 


Timeline Overview

Phase 1-3 (Completed)

January - September  2020

  • Western Tunnel Concrete Walls and Piers Reconstruction
  • Western Tunnel Concrete Roof Slab Reconstruction
  • Central Tunnel Concrete Walls and Piers Reconstruction
  • Central Tunnel Concrete Roof Slab Reconstruction

Phase 4 (Completed)

September - November  2020

  • Eastern Concrete column Construction
  • Eastern Concrete Slab Roof Reconstruction
  • Western Parking Lot Reconstruction
  • Mall lighting and hardscape work

April - June 2021

  • Eastern Concrete Column Construction
  • Eastern Concrete Slab Roof Reconstruction
  • Western Parking Lot Reconstruction
  • Mall lighting and hardscape work
  • Final paving, pavement striping, tunnel lighting, communications and electrical system landscaping, stair installation, and glass enclosure installation.

Project Visualizations

Plans, Maps, and Documents

Community Outreach

Aerial photo of where the tunnel path is located

Project Contacts


Brian Vincent
Project Manager
brian.vincent@lebanonnh.gov
603-448-3112

Patrick Murray
Resident Engineer
pmurray@consulttjtc.com 
802-522-9312

Christopher Robert
E.D. Swett Project Manager
chris@edswett.com
603-224-7401